A recent 9News update on Visy’s glass recycling and manufacturing facility at Stapylton has put one of Queensland’s biggest industrial builds back in the spotlight – and it’s a project Masters Surveying has been involved with since the very beginning.

The project
Visy’s new facility at Stapylton, just south of Brisbane in the Yatala industrial precinct, represents a $500 million investment – the largest Visy has ever made. Once fully operational, the plant will recycle up to 200,000 tonnes of Queensland glass every year and produce around 1 billion bottles annually.
The flow-on benefits are significant. Lifting the average recycled glass content across Visy’s manufacturing network to 70% will reduce the need to transport roughly 40,000 tonnes of glass into Queensland each year – cutting emissions and easing pressure on the state’s supply chain. The new site will also allow Visy to relocate its existing South Brisbane operations, freeing up that site for its next life as the International Broadcasting Centre for the 2032 Olympic Games.
On the employment side, the project is expected to generate around 600 jobs during construction, with 200 ongoing green-collar manufacturing roles once the plant is operational – bringing Visy’s total Queensland workforce to more than 1,000 people.

Where construction stands
Progress on site has been steady through 2025. Frames for the two new glass furnaces went up in June, foundations and structural steel were completed by July, and City of Gold Coast councillors toured the site in August to see the build firsthand. With completion anticipated in 2026, the facility is on track to become a cornerstone of Queensland’s glass manufacturing and recycling capacity.

Masters Surveying’s surveying role at Visy’s Stapylton glass plant
Masters Surveying’s involvement with the Stapylton site goes back to 2021, when we were originally engaged by GHD to carry out a full detail and identification survey of Visy’s existing beverage and board operations, as well as the adjacent greenfield land earmarked for the new glass plant.
Since then, our role has grown considerably. We’ve been engaged directly by Visy in a Project Surveyor capacity, coordinating survey activity across the site, and we’ve worked alongside Timms Group on bulk earthworks, along with a number of subcontractors on structural steel and concrete setout, underground services, and general building setout.
Our work on site has included:
- Civil earthworks and machine control – monitoring progress claim quantities and conformance
- SMP setout for plant and other structural elements
- Miscellaneous site setout across a wide range of site aspects
- Capture of in-ground services, including modelling of trenches and pipelines
- Monitoring of the ASRS warehouse slab
It’s been a genuinely rewarding project to be part of – not just for its scale, but for the calibre of the teams we’ve worked alongside, including VISY, GHD, Timms Group, Borderline Plumbing, FPCS, Saunders International, JMC Electrical, Matland Group, Kraftur and Black Fox Industries.

A project we’re proud to have our name on
As construction moves toward completion in 2026, Stapylton stands as one of the more significant industrial projects Masters Surveying has delivered – a reminder of the scale and complexity our team is equipped to handle on major civil and structural works.
You can see more detail on our involvement in the project, including photos from site, on our Stapylton project page.
Have a large-scale civil, structural or industrial project on the horizon? Get in touch with the Masters Surveying team.